project subject:
West Azerbaijan water treatment plants
Geographical location of the project:
West Azerbaijan – Urmia
main contractor:
Rahsara Co
Implementation activities of the plan:
– Construction, transportation, installation and operation of a complete set of power panels and distribution and operation of the treatment plant
– Installation and operation of 20 electric actuators
– Installation of precision instruments for pump houses and storage tanks
– Installation and commissioning of control panels and backwash systems of 4 filter units
– Installation and commissioning of 4 filter control panels
project schedule:
Years of project implementation: 2001-2002
project subject:
Mechanical and electrical equipment of Ardabil drinking water treatment plant
Geographical location of the project:
Ardabil – Ardabil
main contractor:
Rahsara Co
Implementation activities of the plan:
– Construction, transportation, installation and operation of a complete set of power panels and distribution and operation of the treatment plant
– Installation and operation of 2 electromagnetic flowmeters with a diameter of 1000
– Installation and operation of 2 online turbidity meters
– Installation and commissioning of 2 online pH meters
– Installation and operation of 54 electric actuators
– Installation of precision instruments for pump houses and storage tanks
– Installation and operation of PLC system and control system
– Installation and commissioning of control panels and automatic backwash systems of 12 filter units
– Installation and commissioning of 12 filter control panels
– Installation and commissioning of the control and monitoring equipment of the central control room of the treatment plant
project schedule:
Years of project implementation: 2003-2006
project subject:
The third line of Meshkinshahr treatment plant
Geographical location of the project:
Ardabil – Meshkin Shahr
main contractor:
Rahsara Co
Implementation activities of the plan:
– Installation and commissioning of 2 flowmeters
– Installation and operation of 1 online turbidity meter
– Installation and operation of an online pH meter
– Installation and operation of 10 backwash system electric actuators
– Completion of the PLC system and control system of the treatment plant
– Installation and operation of control panels and automatic backwash systems
– Installation and operation of 8 filter control panels
– Completing the control and monitoring equipment of the central control room and the monitoring equipment of the water and sewage company and the telemetry system of the treatment plant with the central office
project schedule:
Years of project implementation: 2014-2015
project subject:
project subject:
Meshkin water treatment plant of the city
Geographical location of the project:
Ardabil – Meshkin Shahr
main contractor:
Rahsara Co
Implementation activities of the plan:
– Construction, transportation, installation and operation of a complete set of power panels and distribution and operation of the treatment plant
– Construction, transportation and installation of main power and distribution panels of the treatment plant
– Installation and operation of 2 flowmeters
– Installation and operation of 2 online turbidity meters
– Installation and commissioning of 2 online pH meters
– Installation and commissioning of 35 electric actuators
– Installation of precision instruments for pump houses and tanks
– Installation and operation of PLC system and control system
– Installation and operation of control panels and automatic backwash systems
– Installation and operation of 8 filter control panels
– Installation and commissioning of control and monitoring equipment of the central control room
project schedule:
Years of project implementation: 2003-2006
project subject:
Design and construction of the sanitary sewage treatment house of the settlement replacing the submerged villages in the Khoda Afarin dam reservoir
Geographical location of the project:
East Azerbaijan – God bless you
main contractor:
Rahsara Co
Implementation activities of the plan:
– Construction and installation of power and control panels of the treatment plant
– Installation and operation of 5 instruments of sewage treatment plant
project schedule:
Years of project implementation: 2018-2019